2015 Road Works Program

POSTED ON 15 Dec 2015 2 Comments

Owner: City of Airdrie

Project Name: 2015 Road works Program Contract 1- Road Rehabilitation

Jobsite Location: Various locations in the City

Value of Project: $ 1.64 Million

Prime Contractor: ALSA Road Construction Ltd.

Project Scope: The contract included the partial reconstruction of roads on East Lake Blvd, Main Street, Centre Ave, Albert Street, Edmonton Trail, East Lake Avenue and East Lake Link. The work consisted of removing and replacing sections of damaged curb & gutter, and driveways with new concrete; Milling existing asphalt and then providing asphalt overlay over the milled areas. Prior to the milling, existing cracks were filled and failed areas were repaired with full depth asphalt (600mm in depth).Finally line painting was installed and the roads were opened to traffic.

2 comments on “2015 Road Works Program”

  1. Hello sir its Manjit here I m looking for a job.if u have any job then please contact me my home no-4034506969 & cell no-3069200594 Thanks

    1. Hi Manjit. We are always accepting new applications.
      Please stop by the office to fill out an application form Monday to Friday, 8:00-4:30, or email your resume to hr@alsaroad.com.
      Thank you.

LEAVE A COMMENT

Your email address will not be published. Required fields are marked *

LATEST POSTS


POPULAR POSTS