Blog

BY Alsa Road

2015 Road Works Program

POSTED ON 15 Dec 2015 Leave a comment

Owner: City of Airdrie

Project Name: 2015 Road works Program Contract 1- Road Rehabilitation

Jobsite Location: Various locations in the City

Value of Project: $ 1.64 Million

Prime Contractor: ALSA Road Construction Ltd.

Project Scope: The contract included the partial reconstruction of roads on East Lake Blvd, Main Street, Centre Ave, Albert Street, Edmonton Trail, East Lake Avenue and East Lake Link. The work consisted of removing and replacing sections of damaged curb & gutter, and driveways with new concrete; Milling existing asphalt and then providing asphalt overlay over the milled areas. Prior to the milling, existing cracks were filled and failed areas were repaired with full depth asphalt (600mm in depth).Finally line painting was installed and the roads were opened to traffic.

LEAVE A COMMENT

Your email address will not be published. Required fields are marked *

LATEST POSTS


POPULAR POSTS